Stingray's Mineral Resource Update Confirms, Reclassifies and Expands Oxide Copper at El Pilar

Peter Mordaunt, CEO and Chairman of Stingray Copper Inc. ("Stingray")(TSX: SRY)(TSX: SRY.WT) is pleased to report that exploration and development work at the El Pilar Oxide Copper Project in Sonora, Mexico over the last year has resulted in an updated mineral resource. Independent Mining Consultants, Inc. ("IMC") of Tucson, Arizona developed the updated mineral resource for the El Pilar Oxide Copper Project. The new mineral resource is based on an updated mineral resource block model developed by Stingray and IMC personnel.

Table 1 summarizes the mineral resource update. At a 0.20% total copper cutoff grade, the Measured and Indicated Mineral Resource is 276.4 million tonnes at 0.31% total copper representing 1.9 billion pounds of contained copper. The Inferred Mineral Resource contains an additional 42.6 million tonnes at an average grade of 0.29% total copper representing 268 million pounds of contained copper. The estimated tonnage and grade of the Measured and Indicated Resources will form the basis for the feasibility study.


----------------------------------------------------------------------------
Table 1               El Pilar Mineral Resource                   IMC Update
----------------------------------------------------------------------------
             0.25% Total Copper    0.20% Total Copper   0.15% Total Copper
                    Cutoff                Cutoff               Cutoff
----------------------------------------------------------------------------
                                                  lbs                   lbs
Mineral            Total lbs Cu          Total     Cu          Total     Cu
 Resource  tonnes     Cu (mill-  tonnes     Cu (mill-   tonnes    Cu (mill-
 Class     (000's)    (%)  ions) (000's)    (%)  ions)  (000's)   (%)  ions)
----------------------------------------------------------------------------
Measured   68,777  0.366   553   87,690  0.335    646  103,819 0.311    710
Indicated 129,787  0.335   956  188,694  0.300  1,245  241,088 0.273  1,447
Total
 Measured
 &
 Indicated
 Resource 198,564  0.346 1,510  276,384  0.311  1,891  344,907 0.284  2,158
----------------------------------------------------------------------------

----------------------------------------------------------------------------
Inferred   22,806  0.341   171   42,556  0.287    268   72,848 0.240    384
----------------------------------------------------------------------------

This mineral resource meets the "reasonable prospects for economic extraction" conditions of the Canadian National Instrument 43-101 code and also the Australian JORC code. A floating cone evaluation at current spot copper prices and with reasonable operating cost and process recovery assumptions extracts in excess of 95% of the resource presented in Table 1.

Three Main Objectives of Stingray's In Fill Drill Program and Mineral Resource Update:

1) To confirm the Inferred Mineral Resource developed by Magri Consultants of Chile for Noranda/Falconbridge/Xstrata ("Normex") and confirmed by Gary Woods, P. Geo. at El Pilar. Table 2 below outlines the Inferred Mineral Resource defined in the Gary Woods 43-101 F1 Technical Report dated April, 2007 prior to Stingray initiating work at El Pilar. This resource model was the starting point for Stingray's work. Based on significant in fill drilling, Stingray was able to confirm this Inferred Mineral Resource model.


----------------------------------------------------------------------------
Table 2          Noranda/Falconbridge/Xstrata
                    El Pilar Mineral Resource              Gary Woods 43-101
----------------------------------------------------------------------------
             0.25% Total Copper    0.20% Total Copper   0.15% Total Copper
                    Cutoff                 Cutoff              Cutoff
----------------------------------------------------------------------------
                                                  lbs                   lbs
Mineral            Total lbs Cu          Total     Cu          Total     Cu
 Resource  tonnes     Cu (mill-  tonnes     Cu (mill-   tonnes    Cu (mill-
 Class     (000's)    (%)  ions) (000's)    (%)  ions)  (000's)   (%)  ions)
----------------------------------------------------------------------------
Inferred  180,047  0.365  1,448 237,922  0.331  1,736  296,220 0.300  1,959
----------------------------------------------------------------------------

Total
 Resource 180,047  0.365  1,448 237,922  0.331  1,736  296,220 0.300  1,959
----------------------------------------------------------------------------

2) To reclassify the previous Inferred Mineral Resource to a predominately Measured and Indicated Mineral Resource which would increase the geologic confidence for use in a feasibility study. At a 0.25% and 0.20% total copper cutoff grade, Stingray's updated resource model is 90% and 87% Measured and Indicated Mineral Resource respectively (based on the updated Mineral Resource numbers).When compared to the previous Inferred Mineral Resource in Table 2, the updated reclassified Measured and Indicated Resource at both the 0.25% and 0.20% total copper cutoff is more than 100% of the previous Inferred Mineral Resource, respectively.

3) Finally, to expand the copper contained within the higher confidence mineral resource calculation. Additional drilling has resulted in the expansion of the previous Inferred Mineral Resource at a 0.25% total copper cutoff grade and a 0.20% total copper cutoff grade by 16% and 25% respectively, now principally reclassified as a Measured and Indicated Mineral Resource respectively (based on the updated Mineral Resource numbers).

In summary, the updated Mineral Resource at El Pilar has confirmed, reclassified and expanded on the previous work conducted by Magri Consultants for Normex that was verified in the 43- 101 F1 Technical Report authored by Gary Woods (April, 2007). The updated Mineral Resource, which is principally now a Measured and Indicated Mineral Resource was calculated by IMC of Tucson. This reclassification gives Stingray geoscientific confidence for the feasibility study that is ongoing. It is also worthy to note that the El Pilar Mineral Resource is still open in 2 directions and that the source for this copper mineralization has not been identified and represents a future exploration target.

Description of the Resource Model

The drill hole database available for the updated resource model consists of 255 drill holes which represent 52,809 meters of drilling. The drill hole database was provided by Stingray, and has not been audited by IMC. The highest total copper assays were examined to determine if any grade caps or cuts were warranted. It was determined that capping was not required. An interpretation of the rock types was done by Stingray personnel and incorporated into the block model. IMC reviewed and accepted the interpretation. The rock types are important for density determination, but were not directly used for block grade estimation. The copper grades of the resource blocks were estimated by kriging. Three structural zones and a copper grade zone, developed at a total copper cutoff of 0.1%, were used to control block grade estimation. A maximum of ten 5 meter drill hole composites were used to estimate grades for the 10 meter high model benches. This relatively small number of composites was used to avoid over-smoothing the block grades in the model. Bulk densities were assigned to model blocks by lithology type, based on a large amount of specific gravity tests performed by Normex. These bulk densities are also the subject of work by Metcon Research Inc. as part of the ongoing metallurgical column test work in their laboratory in Tucson, Arizona.


----------------------------------------------------------------------------
Table 3                       Bulk Densities
----------------------------------------------------------------------------
Lithology                                   Bulk Density      Tonnes (000's)
 Code        Description                           (t/m3)         Per Block
----------------------------------------------------------------------------
103          OB - Overburden                        2.17               8.68
----------------------------------------------------------------------------
102          MZ - Monzonite                         2.53              10.12
----------------------------------------------------------------------------
201          CGI - Intrusive Conglomerate           2.29               9.16
----------------------------------------------------------------------------
202          CGIV - Transition Conglomerate         2.28               9.12
----------------------------------------------------------------------------
203          CGV - Volcanic Conglomerate            2.30               9.20
----------------------------------------------------------------------------
204          Fault                                  2.36               9.44
----------------------------------------------------------------------------
205          IBX - Incipient Breccia                2.46               9.84
----------------------------------------------------------------------------
210          CGI+ v Transition Conglomerate         2.28               9.12
----------------------------------------------------------------------------

A resource classification was assigned to the blocks based on a combination of the number of holes available for kriging and the kriging standard deviation. IMC examined the classification on cross sections and believes it is reasonable. Measured blocks generally correspond to the northern area of the deposit where the drill spacing is about 70m. This also corresponds to the area of the deposit where the starter pit will be located.

It is the opinion of IMC that the updated block model is adequate for feasibility level evaluations of the El Pilar Project.

Independent Mining Consultants, Inc. (IMC) of Tucson, Arizona Mining Engineer Mike Hester is the Qualified Person for the technical information in the Mineral Resource update provided herein.

Stingray is well financed to complete the feasibility study at El Pilar, with approximately $18M in the treasury. The Corporation is working to conclude a feasibility study for El Pilar by the end of Q1/09.

Website: www.stingraycopper.com


TSX Symbol:    Common Shares - "SRY"    Issued: 58,725,982 common shares
               Warrants - "SRY.WT"              20,850,000 warrants

Certain Statements presented herein may constitute "forward-looking statements". Such forward-looking statements may include potential mineralization, resources and reserves, conclusions of prefeasibility and feasibility studies, estimates of future production, capital and operating costs, prices of metals and other known and unknown risks. These and other factors and uncertainties may cause material differences from future results as expressed or implied by these forward-looking statements. These risks, uncertainties and other factors include but are not limited to the risks involved in the exploration, development and mining business.


Tags: ,Manufacturing and Production:MiningandMetals, ,ID,TORONTO, ONTARIO
   _   _

  care2 logo   digg logo   blogger logo   newsfeeder logo   netscape logo  
Is your favorite bookmark site missing? Ask for it.
marker


Sponsor Links:

Writers Wanted
Help NewsBlaze provide daily news, including top stories, Home and Garden, Technology, The Environment and more. NewsBlaze Writer
Relevant Sites:

NewsBlaze 

Copyright © 2004-2008 NewsBlaze LLC
Use of this website is subject to our Terms of Service and Privacy Policy       Support    Press Room